November has been a highly productive month for the Swarna Estate development. The commitment to steady progress remains strong, with multiple milestones achieved and new phases set to commence shortly. The on-ground team continues to maintain impressive momentum as the estate moves closer each month toward becoming a well-connected, contemporary, and thriving neighbourhood.
Earthwork Progress
Earthworks for Stage 1 and Stage 2 are officially complete. These foundational works prepare the land for future construction activities, ensuring it is suitable for roads, utilities, and new homes.
Basin Excavation
The basin excavation has also been completed, marking a significant step toward long-term water and stormwater management across the estate. This infrastructure will play a vital role in providing efficient drainage and reducing flood risk for the community.
Sewer Works for Stages 1 & 2
Sewer installation for Stage 1 and Stage 2 is now complete. With this essential service in place, the development is well positioned to progress smoothly into the next construction stages.
Drainage Works
Drainage works for both stages are now nearing completion. These systems are crucial in redirecting stormwater away from streets and homes, supporting the estate’s long-term safety and durability.
Road Boxing for Stage 1 & 2
Road boxing and subgrade preparation have commenced for both stages, initiating the early phase of constructing the estate’s internal road network.
Future Construction
Capping layer installation for Stage 1 and Stage 2
Road crossings for Stage 1
These completed milestones continue to strengthen the foundation of Swarna Estate. Further updates will be shared as development progresses toward creating a well-planned and vibrant community.