Construction at Swarna Estate continues to advance steadily, with significant infrastructure milestones now achieved across Stage 1 and Stage 2. Civil works remain on schedule as the estate progresses toward full service completion. We are really pleased with the pace of progress on site this month.

Below is the latest update from site.

Current Construction Status

  • Stormwater Basin – Complete

Construction of the stormwater basin has been successfully completed. This key infrastructure element supports long-term water management across the estate.

  • Sewer Infrastructure – Stage 1 & 2 Complete

Sewer installation works across both stages are now finalised, marking a major milestone in underground service delivery.

  • Kerb Construction – Stage 1 & 2 Underway

Kerbing works are progressing well and are shaping the internal streetscape while supporting road drainage.

  • Drainage – Stage 1 & 2 Near Completion

Drainage infrastructure is in its final stages of installation, with only minor works remaining.

  • Electrical Trenching – Stage 1 & 2 Commenced

Trenching for electrical services has commenced across both stages, preparing for future power connectivity.

  • Water & Gas Works – Stage 2 Commenced

Installation of water and gas infrastructure has begun in Stage 2, moving the estate closer to full service readiness.

Upcoming Construction Works

The next phase of construction will focus on:

  • Completion of remaining drainage works in Stage 1 & 2
  • Finalisation of road construction across Stage 1 & 2
  • Preparation for road surfacing and finishing works

With strong progress across all major infrastructure components, Swarna Estate continues to move confidently toward delivering a fully serviced and well-planned residential community.

For further updates, stay connected with us as we share ongoing progress in the coming months.

Enquire Now

Swarna Estate – February Month Construction Updates1 Swarna Estate – February Month Construction Updates2 Swarna Estate – February Month Construction Updates3 Swarna Estate – February Month Construction Updates4 Swarna Estate – February Month Construction Updates5 Swarna Estate – February Month Construction Updates6
Swarna Icon blue

Register your interest now

Highly accessible to everyday conveniences both inside and surrounding the estate, residents of SWARNA are assured an enviable lifestyle and a bright future.

Register

Disclaimer

This masterplan is indicative of current and proposed amenity and infrastructure and is subject to change. The proposed amenity will not be owned or managed by Swarna and timings and outcome are outside of Swarna’s control and subject to delay, development approvals, statutory approvals and construction. Medical Centre and proposed education institutions including the Childcare and primary school are being delivered by third parties and are subject to development approvals, statutory approvals and construction.